Construction Week 4/3 - 4/7/2023

EXHIBIT 1

BEGINNING MONDAY APRIL 3RD SIERRA NEVADA 

CONSTRUCTION WILL BE INSTALLING CONCRETE IMPROVEMENTS ON COTTONWOOD LANE.

WORK ZONE: 4/3 THROUGH 4/7/2023. WORK HOURS: 7:00 AM TO 4:30 PM 

TO FACILITATE THE TIMELY COMPLETION OF THIS WORK, TRAFFIC WILL BE AS FOLLOWS:

COTTONWOOD LANE (COOK WAY TO BARDOT WAY) 4/3-4/7/2023:SHOULDER CLOSURES WILL BE PRESENT THROUGHOUT THE WORK ZONE. TWO-WAY TRAFFIC WILL BE MAINTAINED DURING ALL SHOULDER CLOSURES. 

EXHIBIT 2

BEGINNING MONDAY, APRIL 3RD SIERRA NEVADA 

CONSTRUCTION WILL CONTINUE INSTALLING SEWER & WATER IMPROVEMENTS ON COTTONWOOD LANE BETWEEN HARDIE LANE & US50A/95A.

WORK ZONE: 4/3 THROUGH 4/7/2023. WORK HOURS: 7:30 AM TO 4:30 PM 

TO FACILITATE THE TIMELY COMPLETION OF THIS WORK, TRAFFIC WILL BE LIMITED TO EASTBOUND ONLY TRAVEL BETWEEN US50A/95A & HARDIE LANE. WESTBOUND TRAFFIC WILL BE DETOURED AT HARDIE LANE TO SHADOW LANE TO US50A/95A. 

Also, next week we have a water main turn-off scheduled. Affected residents will be notified. A vicinity map can be found on our Cottonwood Lane project page. This work will take place Wednesday, April 5 from 9 am - 5 pm. 


9903.000_COTTONWOOD SCHEDULE 4.3-4.7.2023
9903.000_COTTONWOOD SCHEDULE 4.3-4.7.2023-2 (002)